Project Description
Design and construct a 6' sidewalk on the East side of Atwater St. from Veterans Boulevard to Hillsborough Boulevard as part of the 2020 Sales Tax Initiative to connect multiple sidewalk to make community more walkable.Project Location
Veterans Blvd. to Hillsborough Blvd.Latest Updates
The consultant RWA was bought by Kimley-Horn a meeting is scheduled to go over the project with them.
The 90% design plan review has been completed, and comments have been returned to the engineer to address as part of the 100% plan development.
The SWFWMD permit has been issued.
Budget
| Phase | Cost |
|---|---|
| Design | $87,555.00 |
| Construction | $398,350.00 |
| Total Budget | $485,905.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 04/15/2024 | 05/15/2026 | |
| Construction | 05/18/2026 | 11/13/2026 |
Project Phase
Design Development
Last Updated
05/06/2026
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Kimley-Horn
Construction Contractor
TBD