Atwater Street Sidewalk Project

Project Description

Design and construct a 6' sidewalk on the East side of  Atwater St. from Veterans Boulevard to Hillsborough Boulevard as part of the 2020 Sales Tax Initiative to connect multiple sidewalk to make community more walkable.

Project Location

Veterans Blvd. to Hillsborough Blvd. 

Latest Updates

The consultant RWA was bought by Kimley-Horn a meeting is scheduled to go over the project with them.

The 90% design plan review has been completed, and comments have been returned to the engineer to address as part of the 100% plan development.

The SWFWMD permit has been issued.

Budget

Phase Cost
Design $87,555.00
Construction $398,350.00
Total Budget $485,905.00
Funding source(s): This project is funded as part of the 2020 Sales Tax Initiative.

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Design Development 04/15/2024 05/15/2026
Construction 05/18/2026 11/13/2026

Project Phase
Design Development

Last Updated
05/06/2026

Project Manager
Raymond Slade

Public Relations
Chad Ray
Email Public Relations

Sponsor Department
Public Works Engineering

Design Engineer/Architect
Kimley-Horn

Construction Contractor
TBD

Sales Tax Project