Project Description
Replacement of Cedar Point Environmental Park pier with enhanced design for seagrass wading tours.Project Location
Cedar Point Environmental Park
2300 Placida Road, Englewood, FL 34224
Latest Updates
Design and Permitting complete. Finalizing bid documents for procurement.Budget
| Phase | Cost |
|---|---|
| Design | $35,000 |
| Construction | $200,000.00 |
| Total Budget | $235,000.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 11/30/2024 | 03/15/2026 | 05/07/2026 |
Project Phase
Design Development
Last Updated
05/07/2026
Project Manager
Lonne Moore
Public Relations
Breanna Benevenga
Email Public Relations
Sponsor Department
Community Services
Design Engineer/Architect
Coastal Engineering Consultants, Inc.