Project Description
This project is a 8' sidewalk on the North side of Chamberlin Blvd. from US-41 to Jacobs St. for improved walkability.Project Location
The project runs along the north side of Chamberlain Blvd. Phase 1 is from US-41 to Jacobs Street. Phase 2 is from Jacobs Street to Campbell Street.Latest Updates
-
The 100% plans are being reviewed and comments are being added to be addressed by the engineer and complete the construction plans and bid documents.
-
The SWFWMD permit has been issued.
Budget
| Phase | Cost |
|---|---|
| Design | $264,983.00 |
| Construction | $2,360,000.00 |
| Total Budget | $2,624,983.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 09/09/2024 | 05/01/2026 | |
| Construction | 08/03/2026 | 02/01/2027 |
Project Phase
Design Development
Last Updated
05/06/2026
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works Engineering