Project Description
Demolition and complete replacement/repair of the vertical seawall and upland walkway at Charlotte Harbor Event and Conference Center.Project Location
Charlotte Harbor Event and Conference Center
75 Taylor Street, Punta Gorda, FL 33950
Latest Updates
Permitting with US Army Corp. awaiting approval for project design.Budget
| Phase | Cost |
|---|---|
| Design | $182,690.00 |
| Construction | $2,500,000.00 |
| Total Budget | $2,682,690.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 11/02/2023 | 05/29/2026 |
Project Phase
Design Development
Last Updated
05/07/2026
Project Manager
Lonne Moore
Public Relations
Breanna Benevenga
Email Public Relations
Sponsor Department
Community Services
Design Engineer/Architect
Coastal Engineering Consultants, Inc.