Project Description
Design and construct a 6' sidewalk on the South side of Clevland Avenue from Duncan Road (SR17) to Riverside Drive as part of the 2020 Sales Tax Initiative for a more walkable community.Project Location
Clevland Ave. from Duncan Rd. (SR17) to Riverside Dr.Latest Updates
-
The 100% construction plans and bid documents have been received, and all review comments have been satisfactorily addressed.
-
Construction of the project is currently on hold until FY27 to allow the Seminole Gulf Railroad to complete the required railroad crossing upgrades.
Budget
| Phase | Cost |
|---|---|
| Design | $62,010.00 |
| Construction | $521,778.00 |
| Total Budget | $583,788.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 04/24/2024 | 07/01/2025 | 07/31/2025 |
| Construction | 03/03/2027 | 09/01/2027 | |
| Turnover & Closeout | 10/04/2027 | 11/01/2027 |
Project Phase
Design Development
Last Updated
05/06/2026
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Weiler Engineering
Construction Contractor
TBD