Cleveland Avenue Sidewalk Project

Project Description

Design and construct a 6' sidewalk on the South side of Clevland Avenue from Duncan Road (SR17) to Riverside Drive as part of the 2020 Sales Tax Initiative for a more walkable community.

Project Location

Clevland Ave. from Duncan Rd. (SR17) to Riverside Dr.

Latest Updates

  • The 100% construction plans and bid documents have been received, and all review comments have been satisfactorily addressed.

  • Construction of the project is currently on hold until FY27 to allow the Seminole Gulf Railroad to complete the required railroad crossing upgrades.

Budget

Phase Cost
Design $62,010.00
Construction $521,778.00
Total Budget $583,788.00
Funding source(s): 2020 Sales Tax CIP

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Design Development 04/24/2024 07/01/2025 07/31/2025
Construction 03/03/2027 09/01/2027
Turnover & Closeout 10/04/2027 11/01/2027

Project Phase
Design Development

Last Updated
05/06/2026

Project Manager
Raymond Slade

Public Relations
Chad Ray
Email Public Relations

Sponsor Department
Public Works Engineering

Design Engineer/Architect
Weiler Engineering

Construction Contractor
TBD

Sales Tax Project