Project Description
The Greater Port Charlotte Street & Drainage MSBU advisory board as part of a sidewalk initiative has requested the design and construction of a new 6' sidewalk on the West side of Dorchester Street, The South side of Bachmann Boulevard and the West side of Yancy Street.Project Location
This project will include the design and construction of new 6-foot sidewalks on the Southside of Bachmann Boulevard from Atwater Street to Dorchester Street, on the West side of Dorchester Street from Bachmann Boulevard to Yancy Street, and the West side of Yancy Street from Dorchester Street to Midway Boulevard.Latest Updates
-
At the recommendation of the Advisory Board, the project was divided into two phases. Phase 1 extends from Midway Boulevard to Peachland Boulevard and is currently in construction phase 2 will start when funding is available.
-
Door hangers will be distributed 24 hours prior to the work on your driveway to give the timeframe for the work and they will knock on your door the day of the start of the work. if you have any questions, please call the number listed on the door hanger.
-
The current contrace completion date is May 15th. A change order is being processed to add 60 days to the contract.
Budget
| Phase | Cost |
|---|---|
| Design | $155,255.00 |
| Construction | $1,700,000.00 |
| Total Budget | $1,855,255.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 07/07/2020 | 02/25/2022 | 03/01/2022 |
| Construction | 02/03/2025 | 05/15/2026 | |
| Turnover & Closeout | 04/06/2026 | 04/30/2026 |
Supporting Materials
Project Phase
Construction
Last Updated
05/06/2026
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Southwest Engineering & Design, Inc. (SED)
Construction Contractor
Andrew Sitework