Englewood East Amenity Replacement

Project Description

Replacement and improvement of playground equipment and shade structure that was damaged during Hurricane Ian along with the installation of an additional pavilion and drinking fountain for community use.

Project Location

Englewood East Park

11120 Sunnydale Ave

Englewood, FL 34224

Latest Updates

Construction permits have been submitted and construction is scheduled to begin June 15, 2026.

Budget

Phase Cost
Design $235,296.70
Construction $176,994.93
Total Budget $412,291.63
Funding source(s):

CMP-Master Planning

Hurricane Recovery

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Construction 08/01/2026 08/31/2026
Turnover & Closeout 09/01/2026 09/30/2026
Englewood East Amenity Replacement Project Image

Project Phase
Construction

Last Updated
05/07/2026

Project Manager
Lacey Solomon

Public Relations
Breanna Benevenga
Email Public Relations

Sponsor Department
Community Services