Project Description
This project is designing and permitting and then constructing two signalized intersections out of the non-signalized intersection along Gasparilla Road.
Design four-way mast arm signalized intersection at Ingram/Ingraham Boulevard at Gasparilla Rd.
Design three-way mast arm signalized intersection at Rotonda East Boulevard at Gasparilla Road.
Project Location
South Gulf Cove area.
The roadway intersection of Gasparilla Road and Ingram /Ingraham Blvd.
The roadway intersection of Gasparilla Road and Rotonda East Blvd.
Project Impacts
Improved safety features and hardening against future storms.Latest Updates
Kimley-Horn is the county’s design engineer for this project.
- Initial surveys, Geotech, subsurface engineering, and coordination with utilities have all been completed
- Rotonda E. intersection design is at 90% design and is currently under review by county staff for comments before proceeding to 100%.
- Ingram / Ingraham intersection signal design is currently at 100% design submittal. County review is complete including a round of plan comments. K-H is currently working towards bid ready documents.
- Kimley-Horm has applied to SWFWMD for an exemption of permit for construction and that exemption has been obtained and is place.
- Ongoing utility coordination to design mast arm locations in a busy right of way.
- Charlotte County Utility Department is working on locating their utilities and providing that info to the EOR as well as planning relocation of utilities in conflict with Mast Arm drill shaft locations.
- The current design schedule is scheduled to be complete by August 2026. The construction bid will immediately follow.
Budget
| Phase | Cost |
|---|---|
| Design | $299,901.00 |
| Construction | $2,000,000.00 |
| Total Budget | $2,299,901.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 04/09/2024 | 12/13/2024 | 12/13/2024 |
| Design Development | 12/16/2024 | 07/22/2026 | |
| Construction | 11/02/2026 |
Project Phase
Design Development
Last Updated
04/30/2026
Project Manager
Zach Patchell
Public Relations
Chad Ray
Email Public Relations
Project Number
TBD
Sponsor Department
Public Work Engineering
Design Engineer/Architect
Kimley-Horn
Construction Contractor
TBD