Project Description
These 3 bridges require design services to implement the FDOT maintenance and repair items for each of the respective bridges.
Bridge #014030 Pellam Boulevard over Auburn Waterway.
Bridge #014043 Wintergarden Avenue over Como Waterway.
Bridge #014069 O'Hara Drive over Atlantus Waterway.
Project Location
Bridge #014030 Pellam Boulevard over Auburn Waterway
Bridge #014043 Wintergarden Avenue over Como Waterway
Bridge #014069 O'Hara Drive over Atlantus Waterway
Latest Updates
Project Activities – May 2026
Construction on the O'Hara Bridge (Bridge No. 014069) is complete.
Construction on the Pellam Bridge (Bridge No. 014030) is complete.
Construction of the Wintergarden Bridge began on March 18, 2026. The bridge will be closed for 45 days to complete the bridge rehabilitation.
This bridge has confirmed Gopher Tortoises within the construction limits. An environmental consultant has been hired to manage the required tortoise mitigation. This process requires an FWC permit, which typically takes 90 days to obtain. Unfortunately, we have exceeded the 90‑day timeframe and the permit is still pending. As a result, we will need to extend the bridge closure until the permit is approved and mitigation can be completed.
Budget
| Phase | Cost |
|---|---|
| Design | $189,895 |
| Construction | $1,149,558.83 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 01/16/2024 | 05/15/2025 | 07/03/2025 |
| Construction | 12/08/2025 | 06/06/2026 |
Project Phase
Construction
Last Updated
05/01/2026
Project Manager
Kelly Slaughter
Public Relations
Chad Ray
Email Public Relations
Project Number
2024001131
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Kimley-Horn Engineers
Construction Contractor
Villa Fuerte Construction


