Project Description
The Deep Creek Street & Drainage MSBU has requested a sidewalk be designed and constructed on Rampart Boulevard. A8' sidewalk is being designed on the North side of Rampart Blvd.Project Location
Rampart Boulevard from Rio De Janeiro Avenue to Navigator Road and Rampart Boulevard to 1457 San Cristobal Avenue.Latest Updates
-
The consultant is finalizing the 90% design plans, which are being developed in coordination with Sales Tax Phases 1 and 2.
-
The consultant is coordinating with FDOT regarding the I-75 overpass segment.
Budget
| Phase | Cost |
|---|---|
| Design | $64,000.00 |
| Construction | $308,000.00 |
| Total Budget | $372,000.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 12/01/2022 | 01/16/2023 | |
| Design Development | 02/01/2023 | 05/04/2026 | |
| Construction | 08/31/2026 | 06/30/2027 |
Project Phase
Design Development
Last Updated
05/06/2026
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Project Number
c412204
Sponsor Department
Public Works Engineering
Design Engineer/Architect
DRMP Inc.
Construction Contractor
TBD