Project Description
The main kitchen, laundry, and associated plumbing equipment has reached the end of it's useful life.With the recent addition of the Jail Imfirmary there is additional space that can now be repurposed. Project
renovates the jail's kitchen and laundry spaces while repurposing additional areas for Facilities and
jail operating inventory warehouse.
Project Location
28571 Airport Rd
Punta Gorda FL
Latest Updates
Progress is being made on the jail kitchen and laundry remodel. Strollo Architects has been engaged as the design consultant, and a kickoff meeting is scheduled for May 1. Preparations are underway to advertise for a Construction Manager at Risk (CMR), with the solicitation expected to be released in the coming weeks.
Budget
| Phase | Cost |
|---|---|
| Design | $700,000 |
| Construction | $7,355,000 |
| Total Budget | $8,055,000.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 11/21/2025 | 02/25/2026 | 02/03/2026 |
| Design Development | 04/01/2026 | 11/28/2026 | |
| Construction | 11/28/2026 | 08/25/2027 | |
| Turnover & Closeout | 08/25/2027 | 11/01/2026 |
Project Phase
Planning and Project Approval
Last Updated
04/23/2026
Project Manager
Scott Brouillard
Public Relations
Brian Gleason
Email Public Relations
Sponsor Department
Public Safety