Project Description
The project will replace two outdated and undersized buildings constructed in 1992 with a single, more efficient, up-to-date facility. The new facility will meet current safety and storm-resiliency standards and will accommodate increased staffing needs and future growth.Project Location
29751 Zemel Rd
Punta Gorda FL 33955
Project Impacts
This project is not expected to cause any disruption to landfill operations.Latest Updates
Progress is underway for the Zemel Road Maintenance and Operations Building. ADG Architects has been secured as the design consultant, and the project is currently pending Board of County Commissioners (BoCC) approval to proceed into the initial design phase.Budget
| Phase | Cost |
|---|---|
| Design | $318,000 |
| Construction | $6,233,000 |
| Other Costs | $130,000 |
| Total Budget | $6,681,000.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 09/18/2025 | 02/10/2026 | |
| Design Development | 04/01/2026 | 11/28/2026 | |
| Construction | 11/28/2026 | 08/25/2027 | |
| Turnover & Closeout | 08/25/2027 | 10/25/2027 |
Project Phase
Planning and Project Approval
Last Updated
04/23/2026
Project Manager
Scott Brouillard
Public Relations
Brian Gleason
Email Public Relations
Project Number
C342601
Sponsor Department
Public Works