Washington Loop over Prairie Creek Bridge Replacement

Project Description

Charlotte County has engaged Kimley-Horn and Associates to design the replacement of the Washington Loop Bridge over Prairie Creek. Originally constructed in 1961, the existing bridge has been subject to overtopping during storm events, resulting in periodic closures. The new bridge will be designed to mitigate these issues by elevating the structure to accommodate greater water volumes and higher flow velocities during flooding events.

Project Location

Washington Loop Road over Prairie Creek

Latest Updates

Project Activities – May 2026

The design team has submitted the Bridge Development Report (BDR), and the County has completed its review and issued approval. The team is now moving forward with the 60% design plans, along with permitting activities for the roadway, bridge, and utilities. The 60% design plans are due January 2027.

Budget

Phase Cost
Design $697,238.14
Funding source(s): Road and Bridge Funding

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Design Development 05/07/2025 09/03/2027
Washington Loop over Prairie Creek Bridge Replacement Project Image

Project Phase
Design Development

Last Updated
05/01/2026

Project Manager
Kelly Slaughter

Public Relations
Chad Ray
Email Public Relations

Project Number
25002277

Sponsor Department
Public Works Engineering

Design Engineer/Architect
Kimley-Horn Engineers