Project Description
Remove hurricane debris from approximately 37 miles of navigable waterways througout the county. Please see attached map that shows which waterways are included in the project.Project Location
There are various navigable waterway systems that are included in this project.Latest Updates
Work began on March 10, 2026. The contractors are currently working in Punta Gorda in the Deltona area. To date, the contractor has removed approximately 1149 cubic yards of debris from the waterways. Work is anticipated to be complete in June.Budget
| Phase | Cost |
|---|---|
| Construction | $800,000 |
| Other Costs | $200,000 |
| Total Budget | $1,000,000.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Construction | 03/10/2026 | 06/09/2026 |
Supporting Materials
Project Phase
Construction
Last Updated
05/07/2026
Project Manager
Karen Bliss
Public Relations
Chad Ray
Email Public Relations
Project Number
2026-072
Sponsor Department
Public Works Engineering
Construction Contractor
Looks Great Services of MS, Inc.